Sunday, 2 February 2014

LAN In A Box - Part 4, Handle it!

It's all well and good having everything in a box for convenience, but if you can't move it some where easily, then it'll never get there. As always, the amount of effort to do something will eventually put you off doing it, so making things easier at the start is always a plus.

With this in mind, and knowing that the box would be easily a two-man lift, handles were always going to be important. More so how they're added as space is limited for both storage and transportation. 

Fixed handles screwed/bolted to the side work, but they'll almost certainly get broken, or break something when they come together with some other object, like a wall, a door frame or a shin. So I opted for cut outs in an arc shape to mirror the inside of the hand. 

First up a template, a 1" forstner bit to make a couple of holes in some plywood...


Then a jigsaw to cut the arc's free hand after a bit of rough marking.


The template clamped onto the side of the box and some swift work with the router to clear the center, followed by a round over bit to smooth the edges...


And it's done. Feel comfy in the hand and should make moving it a lot easier. If I did it again, i'd probably consider some recessed handles like you'd find on a flight case which pop out, but even those aren't perfect for every situation.


Next up power. with the switch roughly where I wanted it, the space to the left had ample room for two 4-ways, 7 sockets total for a single external plug. And there's enough height for a socket mounted power-brick to fit.



I remembered an awesome trick from the internets for this. Photocopy the back of the 4-way, receive scale drawing of the holes to mount with. Genius!



There should almost certainly be another picture here, but I can't find it, you'll just have to accept that they fit for the time being and everything is fine. :)

Thursday, 30 January 2014

TV Unit. Version 4... :(

UPDATE:
As part of the Great Living Room Shuffle and subsequent discovery of needing to move this year, the TV unit ended up being moved and redesigned. Fortunately it's been in the new state for quite a while, which at least means the unit worked while it was where it ended up at the end of this post when originally written.

(Spring 2013)
The TV unit as for quite a while taken up a good area of my lounge and housed plenty of equipment and with the speaker stands as well, it's most of a wall. The problem now is to move it to what is, in all honesty the place it should always have been, it needs to be shorter, so the center third is coming out.

The sub is moving behind the sofa and the HTPC in the bottom left is just coming out of the unit all together as it wasn't getting used.


With the top removed and the two end sections pushed together the top has to be cut down. Sadly, all the cabling i'd carefully done had to be picked apart to put a new shelf in to allow a few extras to be added.


One cut with the power saw, and it's done.



The amp, CD and DVD player all stayed in the same place, although the two players are now on their own shelves with the switch behind the CD player. The other side has the Xbox, Sky receiver and more consoles on the bottom shelf.


Once the cables are in, the unit needs a back on some of it to help make it stable, it's not much but it does a lot to stop it swaying.


The only things thats not changed is the Amp has been replaced with a newer AV receiver and the TV is say on top of a larger center speaker. At least it survived the upgrade and still worked well enough. 




Sunday, 26 January 2014

The Big Desk Move - Pt 9: Odds and Ends

By this point the desk has been done for quite some time, (nearly 2 months) but a few things crop up now and again which work quite well and are worth documenting, if only trivially.

My headphones have NEVER had a decent home. I've tried lots of things and never know what to do with them.

So far int he last few years I've tried:
- Hung them by an ear cup off the front of the desk (which just gets hit by the chair and usually leaves a mark on the desk from the cup fabric)
- Under the screen (usually end sin tangled wires with the mouse and keyboard)
- Left them to the side of the mouse/keyboard (now the laptop is there, so no good. Plus it always tangled.)
- Hung them over the screen itself (obscures part of the screen)
 
Nothing works

I found a metal hook i'd made from some 1/2" x 16 ga. aluminium bar before I got the other hooks which now hold up the laptop PSU. This used to be under the desk and was a bit shabby, but with some extra time with the pliers its turned into a reasonable point to hang the headphones from.



For the time being I've just clamped it in place to see how useful they are in this position. If they get tangled like before I may move it again, but until that happens screwing it into the nice TV mount and leaving a hole if I move it later isn't on the cards.


So far it seems to be a lot better than anything I've done before. I'll probably give it a coat of black paint and some varnish too just so it doesn't look glaringly different to everything else which is either Birch or black currently.

Monday, 20 January 2014

LAN In A Box - Pt3

Well it's about time I do an update to the blog, and the biggest project of recent times has still been LAN in a Box. So here's part three!

At the back of the box is a mount for a patch panel. Normally I wouldn't bother with this, but there's always a chance that a cable could get snagged on something, or pulled sharply which *may* however unlikely it could be, damage the port on the switch. As the switch was generously donated to the project I really don't want to damage it as getting a replacement would be incredibly hard (to pay for more than anything). With with the cables always connected the switch also doesn't have much wear on the ports with cables being plugged/unplugged all the time.

The patch panel will just link into the ports and transpose them up to the top to where the cables reels are stored.

With that in place the back gets cut to fit to close off the rear of the panel.


To fix the panel in, recessed nuts on bolts fed from the rear make fixed studs to bolt the panel onto, and it's nicely held in place.


So far so good. The reels fit in the top in front of the panel behind the lip and there's plenty of space for the rest of the bits.



the test weekend was pretty good, although it wasn't fully patched due to a few problems with tools (lost my punch down tool, oops). Will update this again soon with more of the details of LIAB, and perhaps some other things.

Tuesday, 26 November 2013

LAN In A Box - Pt2

This is the second post about LAN in a Box, the plan to have a completely self contained unit for a 30-40 person LAN in one single container for easy carriage, storage and deployment.

The lest post finished with the cable shelf being reinforced as it was sagging down into the switch space. So here is the shelf installed. Neat.


Underneath there's plenty of room for the switch and the power strips to distribute to everything (sounds fancy, it's a pair of 4 ways). Above this there'll be a box with a patch panel from all the switch ports. Seems excessive but inevitably someone will kick or trip on a cable and it'll tug at the ports, rather than damage the cwitch, this may only damage the panel, or the cable itself. Either way, better than the shiny 4900.


About this time I was wondering how to make the bundles of cables pack into the box neatly, they've always been a bit of a pain to put away and to lay out and they inevitably become twisted and snag or don't sit flat.

After a while I decided to try and make some reels as there are only two bundles it's not going to be a huge task to start on and they will hopefully keep everything together.

Cutting a circle is a pain at times and after getting about half way round with a jigsaw I realised how stupid I was being. Behind me was a perfectly good bandsaw PERFECT for this. The system worked...


... and in about 5 minutes I'd made all four sides to the reels.


The reel centers are more 18mm plywood, with one side trimmed so as not to cut into the cables if they're tight. Screw in from each side and they're done!


They hold a full bundle perfectly and sit side by side, after a quick test roll out they seem to work pretty well, we'll see how well in November.


Once again, more to come ready for the weekends test.




Sunday, 10 November 2013

LAN In A Box - Pt1

For a long while I've been doing LANs and the problem between them is storing everything neatly out of the way. Fortunately I've got a decent size cupboard that everything fits in, but it's still in a lot of misc gear. Eventually a giant tea crate fit the bill and was sturdy enough to carry almost everything with the exception of the switches and the server.


Conveniently there's a massive piece of plywood in the garage that should make a new box with ease.


Thanks to Dave (Pumpkin) who chatted about LIAB a while back for the uber-switch, nice big Cisco should be ample. 48 GBit ports and takes care of DHCP duties for the LAN. Pretty much the biggest thing going into the box so it has to be the basis for the foot print.


Base and sides cut, will be almost as tall as it is wide and just deep enough for the switch, power cables and cat 5 cables coming from the front. The box has to fit into a specific place in my house so cant be too much bigger than the original tea crate.


That said, its a trade off to make sure everything fits, so it'll be pretty close over all.


Above the switch is a shelf, just over 2U above the base to leave enough room for power bricks and plugs, as well as a second switch if needed.


The shelf slots into the grooves nicely but needs reinforcing.


End of the first session of building and the shelf is having a reinforcing strip added to the front to give some grip to pull it out and stop it deflecting once it has cables and such on top.


More to come in the next couple of days as the first use is next weekend at THaTLAN 2

Thursday, 7 November 2013

Cooking with Music

With the purchase of the new MiniTop for the car, and the subsequent lack of GPS making it a bit useless for that, the reserve function got setup.
In the kitchen before this was a laptop on top of the fridge and some speakers under the upper cupboards with a sub on top. 

Replacing all of this:


...with this:

The volume knob also shifted with the reduction in cabling to under the cupboards against the fridge. Substantially tidier than before and sit next to the tablet itself.


The tablet will go into a wooden surround to hold it in place more securely, once it's made, which it isnt yet. So in the mean time it'll sit on top of the chopping board.

So far it's a success! although it's not hooked up to the music store as yet. But it will be.